Right-clicking a Gantt bar or the chart background opens a context menu with quick actions. The menu adapts based on what you click — a task bar, a milestone, a summary bar, empty space, or a dependency line.

Bar Context Menu

Right-click any activity bar to see these options:

ActionShortcutDescription
Scroll to ActivityCentres the grid on this activity's row
Activity DetailsEnterOpens the Activity Details side panel for this activity
Edit Start DateOpens the date picker pre-filled with the current early start
Edit Finish DateOpens the date picker pre-filled with the current early finish
Edit DurationOpens the duration editor for original or remaining duration
Add RelationshipStarts interactive relationship drawing from this activity
Set ConstraintOpens the constraint picker (Must Start On, SNET, FNLT, etc.)
Mark as CriticalToggles a manual critical-path override flag
Copy Activity IDCtrl+CCopies the activity ID to the clipboard
Delete ActivityDelRemoves the activity (with confirmation)

Milestone-Specific Options

When you right-click a milestone diamond, the menu adds:

ActionDescription
Toggle Start/FinishSwitch between start milestone and finish milestone type
Edit Milestone DateOpens a single date picker for the milestone date

Summary Bar Options

Right-clicking a WBS summary bar shows:

ActionDescription
Expand All ChildrenExpands every nested WBS level beneath this node
Collapse All ChildrenCollapses all child rows under this summary
Select All ActivitiesSelects every activity within this WBS scope

Background Context Menu

Right-click an empty area of the Gantt chart (not on a bar) to see:

ActionDescription
Zoom to FitAutomatically scales the time axis to fit all visible activities
Zoom to SelectionZooms to the date range of the currently selected activities
Zoom to Data DateCentres the view on the schedule's data date
Go to DateOpens a date picker to jump the Gantt to any date
Show/Hide Data Date LineToggles the data date marker line
Show/Hide Baseline BarsToggles primary baseline bar visibility
Gantt SettingsOpens the full Gantt Settings panel

Dependency Line Context Menu

Right-click a relationship line between two bars:

ActionDescription
Edit RelationshipOpens the relationship editor with type and lag fields
Delete RelationshipRemoves the predecessor/successor link (with confirmation)
Show PredecessorScrolls to and highlights the predecessor activity
Show SuccessorScrolls to and highlights the successor activity

Keyboard Alternative

You can also trigger the context menu from the keyboard:

  1. Select an activity row in the grid.
  2. Press Shift+F10 (or the Menu key) to open the context menu at the selected bar's position.

Tips

Quick navigation

Use Scroll to Activity from the Gantt context menu when you have found an activity in the grid and want to see its bar position on the timeline.

Bulk operations

Select multiple activities in the grid first, then right-click any selected bar. Bulk-applicable actions (Delete, Set Constraint) will apply to the entire selection.