Skip to main content

Schedule Options

Applies to: Pro · Enterprise Last updated: 27-Feb-2026

Overview

The Schedule Options dialog configures how the CPM engine calculates your schedule. Options are organised in three tabs: General, Calculation, and Advanced. You can run the schedule calculation directly from this dialog.

Prerequisites

  • Active Pro or Enterprise subscription
  • Editor Mode enabled
  • At least one project loaded

Opening Schedule Options

Open from:

  • Editor Toolbar → Schedule Settings button
  • Grid Toolbar → Project menu → Schedule Options
  • Press F9 to open the dialog and calculate in one step

General Tab

OptionTypeDefaultDescription
Data DateDate pickerCurrent project data dateThe status date for scheduling
Retained LogicToggleOnRespect predecessor logic for in-progress activities
Progress OverrideToggleOffAllow progress to override logic constraints

Retained Logic vs Progress Override

  • Retained Logic (recommended): In-progress activities still respect predecessor relationships. If a predecessor is delayed, the remaining work on in-progress successors adjusts accordingly.
  • Progress Override: In-progress activities ignore predecessor logic. Useful when actual progress has moved ahead of the planned logic.

Only one of these options should be enabled at a time.

Calculation Tab

OptionTypeDefaultDescription
Total Float CalculationSelectFinish FloatHow total float is computed
Lag CalendarSelectPredecessorWhich calendar to use for lag duration
Connect Open EndsToggleOnCreate implicit links from open-ended activities to the project finish
Longest Path CriticalToggleOffIdentify the longest path through the network

Total Float Calculation

MethodFormula
Finish FloatLate Finish − Early Finish
Start FloatLate Start − Early Start

Most practitioners use Finish Float (the default).

Lag Calendar

OptionDescription
PredecessorLag is measured using the predecessor's calendar
SuccessorLag is measured using the successor's calendar
LongestUses whichever calendar produces the longer duration

Advanced Tab

OptionTypeDefaultDescription
Ignore CompletedToggleOffExclude completed activities from the calculation
Near-Critical ThresholdNumber (days)10Activities with total float at or below this value are flagged as near-critical (range: 0–365 days)

Defaults

Options initialise in a three-layer merge:

  1. System defaults — built-in Kazinex defaults
  2. XER-embedded options — options imported from the P6 schedule file
  3. User-saved options — your last saved configuration for this project

Your manual changes override all previous layers.

Running the Schedule

Click the "Schedule (F9)" button at the bottom of the dialog to execute the CPM engine immediately. The calculation runs with the current options, and results appear in the Schedule Results Panel.

Tips & Best Practices

  • Leave Retained Logic enabled for most projects — it produces the most accurate dates
  • Enable Connect Open Ends to prevent open-ended activities from having infinite float
  • Enable Longest Path Critical for multi-calendar projects where the traditional critical path may not correctly identify the longest duration chain
  • The Near-Critical Threshold of 10 working days is a good starting point; adjust based on project risk tolerance