Column Definitions

Available in: All plans
Last updated: 26-Feb-2026

Overview

The Kazinex activities grid supports 265 columns across 13 categories. This reference documents every column — its name, data type, and description. Use this when configuring the Column Chooser or interpreting data in the grid.

Data Types

TypeDescriptionFormat Example
stringText valueA1010, Pour Foundation
numberNumeric value42, 1.5
dateCalendar date15-Mar-2026
durationTime span (hours or days)80h, 10d
booleanTrue/false toggle✅ / —
percentPercentage value85.5%
costCurrency amount$125,000.00

Dynamic Columns

Three categories are populated dynamically from your uploaded file:

  • Activity Codes — Created from the activity code types defined in P6 (e.g., Area, Phase, Responsibility)
  • User Defined Fields (UDFs) — Created from UDF definitions in the XER file
  • Predecessors/Successors — Relationship details generated from logic data

These columns appear automatically in the Column Chooser after import.


1. General (20 columns)

Core activity identification and configuration fields.

Column NameIDData TypeDescription
Activity IDtask_codestringUser-visible activity code identifier
Activity Nameactivity_namestringActivity name or description
Activity Typeactivity_typestringTask type: Task Dependent, Milestone, LOE, etc.
StatusstatusstringNot Started, In Progress, or Completed
Duration Typeduration_typestringFixed Duration, Fixed Units, Fixed Units/Time, etc.
WBSwbs_idnumberWork Breakdown Structure identifier
Project IDproject_idnumberProject identifier
Calendarcalendar_idnumberCalendar assigned to the activity
GUIDguidstringGlobally unique identifier
Locationlocation_idnumberLocation reference
Createdcreate_datedateDate the activity was created
Modifiedupdate_datedateDate of last modification
Created Bycreate_userstringUser who created the activity
Modified Byupdate_userstringUser who last modified the activity
PriorityprioritystringTop, High, Normal, or Low
Review Requiredreview_flagbooleanWhether the activity requires review
LockedlockedbooleanWhether the activity is locked for editing
Auto Compute Actualsauto_computebooleanAutomatically compute actual values
Estimate Weightest_weightnumberWeight used in estimating
Percent Complete Typecomplete_pct_typestringHow % complete is calculated: Physical, Duration, or Units

2. Dates (33 columns)

All date-related fields including planned, actual, early/late (CPM), baseline, and constraint dates.

Column NameIDData TypeDescription
Scheduled Datesscheduled_date_rangestringEarly Start → Early Finish range
Actual Datesactual_date_rangestringActual Start → Actual Finish range
Remaining Datesremaining_date_rangestringRemaining Early Start → Remaining Early Finish range
Baseline Datesbaseline_date_rangestringBL Start → BL Finish range
StartstartdateCurrent start: Actual Start if started, else Early Start
FinishfinishdateCurrent finish: Actual Finish if complete, else Early Finish
Planned Startplanned_startdatePlanned start date
Planned Finishplanned_finishdatePlanned finish date
Early Startearly_startdateCPM early start (forward pass)
Early Finishearly_finishdateCPM early finish (forward pass)
Late Startlate_startdateCPM late start (backward pass)
Late Finishlate_finishdateCPM late finish (backward pass)
Actual Startactual_startdateWhen work actually started
Actual Finishactual_finishdateWhen work actually finished
Expected Finishexpected_finishdateForecasted completion date
Restart Daterestart_datedateDate to resume suspended work
Re-Finish Datereend_datedateAdjusted finish for suspended work
Remaining Late Startrem_late_startdateLate start for remaining work
Remaining Late Finishrem_late_finishdateLate finish for remaining work
Constraint Typeconstraint_typestringPrimary constraint (ASAP, ALAP, MSO, MFO, etc.)
Constraint Dateconstraint_datedatePrimary constraint date
Constraint Type 2constraint_type2stringSecondary constraint type
Constraint Date 2constraint_date2dateSecondary constraint date
Suspend Datesuspend_datedateDate work was suspended
Resume Dateresume_datedateDate work resumed after suspension
External Early Startexternal_early_startdateImposed early start (external constraint)
External Late Finishexternal_late_finishdateImposed late finish (external constraint)
Primary Constraint Dateprimary_constraint_datedatePrimary constraint date
Secondary Constraint Datesecondary_constraint_datedateSecondary constraint date
Anticipated Startanticipated_startdateAnticipated start date
Anticipated Finishanticipated_finishdateAnticipated finish date
BL Startbl_startdateBaseline start: BL Actual Start if started, else BL Early Start
BL Finishbl_finishdateBaseline finish: BL Actual Finish if complete, else BL Early Finish

3. Durations (26 columns)

Duration values, float calculations, and schedule variance metrics.

Column NameIDData TypeDescription
Original Durationoriginal_durationdurationBaseline duration in hours
Remaining Durationremaining_durationdurationDuration left to complete
Actual Durationactual_durationdurationActual duration worked
At Completion Durationat_completion_durationdurationActual + Remaining duration
BL Durationbl_project_durationdurationProject baseline duration
Variance - BL Durationvariance_bl_project_durationdurationAt Completion - Baseline duration (negative = overrun)
Variance - BL Startvariance_startnumberDays difference from baseline start (positive = delayed)
Variance - BL Finishvariance_finishnumberDays difference from baseline finish (positive = delayed)
Total Floattotal_floatdurationTotal float in hours
Free Floatfree_floatdurationFree float (without affecting successors)
Remaining Floatremaining_floatdurationRemaining float (Late Finish - Remaining Early Finish)
Drivingdriving_pathbooleanOn driving (critical) path
Working Daysworking_daysdurationWorking days between start and finish (calendar-aware)
Calendar Dayscalendar_daysdurationCalendar days between start and finish
Ahead/Behind Scheduleahead_behind_schedulenumberDays ahead (positive) or behind (negative)
Baseline Variance (Days)baseline_variance_daysnumberDays variance from baseline dates
Actual Working Daysactual_working_daysdurationActual working days elapsed
Remaining Working Daysremaining_working_daysdurationRemaining working days to finish
Days to Godays_to_gonumberCalendar days until planned finish
Is Criticalis_criticalbooleanTotal float ≤ 0
Is Near Criticalis_near_criticalbooleanFloat between 0 and 10 days
Float Trendfloat_trendstringIncreasing, Stable, or Decreasing
Criticality Indexcriticality_indexnumber0–100 criticality score
Driving Path (Enriched)drivingPathstringPath label if on driving path
Longest Pathlongest_pathbooleanIs on the longest path
Secondary Floatsecondary_floatdurationFloat if driving predecessor removed

4. Percent Complete (43 columns)

All percentage-based progress metrics including physical, duration, cost, and baseline comparisons.

Column NameIDData TypeDescription
Physical % Completephysical_pct_completepercentManually entered physical progress
Duration % Completeduration_pct_completepercentBased on total units (labor + nonlabor)
Labor Units % Completelabor_units_pct_completepercentActual work / target work
Nonlabor Units % Completenonlabor_units_pct_completepercentActual nonlabor / at completion nonlabor
Cost % Completecost_pct_completepercentActual cost / at completion cost
Expense Cost % Completeexpense_cost_pct_completepercentActual expense / at completion expense
Labor Cost % Completelabor_cost_pct_completepercentActual labor cost / at completion labor cost
Material Cost % Completematerial_cost_pct_completepercentActual material cost / at completion material cost
Nonlabor Cost % Completenonlabor_cost_pct_completepercentActual nonlabor cost / at completion nonlabor cost
Units % Completeunits_pct_completepercentActual units / at completion units
BL Activity % Completebl_project_activity_pct_completepercentExpected activity % per baseline at current date
BL Duration % Completebl_project_duration_pct_completepercentBL actual duration / BL total duration
BL Cost % Completebl_project_cost_pct_completepercentBL actual cost / BL total cost
BL Performance % Completebl_project_performance_pct_completepercentBL actual cost / BL target cost
BL Labor Cost % Completebl_project_labor_cost_pct_completepercentBL actual labor cost / BL labor cost
BL Nonlabor Cost % Completebl_project_nonlabor_cost_pct_completepercentBL actual nonlabor cost / BL nonlabor cost
BL Material Cost % Completebl_project_material_cost_pct_completepercentBL actual material cost / BL material cost
BL Expense Cost % Completebl_project_expense_cost_pct_completepercentBL actual expense cost / BL expense cost
BL Labor Units % Completebl_project_labor_units_pct_completepercentBL actual labor units / BL labor units
BL Nonlabor Units % Completebl_project_nonlabor_units_pct_completepercentBL actual nonlabor units / BL nonlabor units
BL Units % Completebl_project_units_pct_completepercentBL actual units / BL total units
BL Physical %bl_project_physical_pctpercentBaseline physical % complete
BL Schedule %bl_project_schedule_pctpercentBaseline schedule % complete
BL Cost % of Budgetbl_project_cost_pct_of_budgetpercentBL actual cost / BL budgeted cost
BL Duration % of Originalbl_project_duration_pct_of_originalpercentBL actual duration / BL original duration
BL % Complete Typebl_project_percent_complete_typestringBaseline calculation method
Variance - BL Activity %variance_bl_project_activity_pctpercentCurrent - baseline activity % (positive = ahead)
Variance - BL Duration %variance_bl_project_duration_pctpercentCurrent - baseline duration %
Variance - BL Cost %variance_bl_project_cost_pctpercentCurrent - baseline cost %
Variance - BL Performance %variance_bl_project_performance_pctpercentCurrent - baseline performance %
Variance - BL Labor Cost %variance_bl_project_labor_cost_pctpercentCurrent - baseline labor cost %
Variance - BL Nonlabor Cost %variance_bl_project_nonlabor_cost_pctpercentCurrent - baseline nonlabor cost %
Variance - BL Material Cost %variance_bl_project_material_cost_pctpercentCurrent - baseline material cost %
Variance - BL Expense Cost %variance_bl_project_expense_cost_pctpercentCurrent - baseline expense cost %
Variance - BL Labor Units %variance_bl_project_labor_units_pctpercentCurrent - baseline labor units %
Variance - BL Nonlabor Units %variance_bl_project_nonlabor_units_pctpercentCurrent - baseline nonlabor units %
Variance - BL Units %variance_bl_project_units_pctpercentCurrent - baseline units %
Variance - BL Physical %variance_bl_project_physical_pctpercentCurrent - baseline physical %
Variance - BL Schedule %variance_bl_project_schedule_pctpercentCurrent - baseline schedule %
Variance - BL Cost % of Budgetvariance_bl_project_cost_pct_of_budgetpercentCurrent - baseline cost % of budget
Variance - BL Duration % of Originalvariance_bl_project_duration_pct_of_originalpercentCurrent - baseline duration % of original
Performance % Completeperformance_pct_completepercentActual cost / target cost
% Schedule Completepercent_schedule_completepercentPercentage of schedule duration complete

5. Units (17 columns)

Labor and nonlabor resource unit quantities.

Column NameIDData TypeDescription
Primary Resourceprimary_resourcenumberPrimary resource identifier
Budgeted Labor Unitsplanned_labor_unitsnumberBudgeted work hours
Remaining Labor Unitsremaining_labor_unitsnumberWork remaining in hours
Actual Labor Unitsactual_labor_unitsnumberWork completed in hours
Actual This Period Laboractual_this_period_labornumberWork this period in hours
Budgeted Nonlabor Unitsplanned_nonlabor_unitsnumberBudgeted equipment/nonlabor units
Remaining Nonlabor Unitsremaining_nonlabor_unitsnumberEquipment remaining
Actual Nonlabor Unitsactual_nonlabor_unitsnumberEquipment used
Actual This Period Nonlaboractual_this_period_nonlabornumberEquipment this period
BL Labor Unitsbl_project_labor_unitsnumberBaseline labor units
BL Actual Labor Unitsbl_project_actual_labor_unitsnumberBaseline actual labor units
BL Remaining Labor Unitsbl_project_remaining_labor_unitsnumberBaseline remaining labor units
BL Nonlabor Unitsbl_project_nonlabor_unitsnumberBaseline nonlabor units
BL Actual Nonlabor Unitsbl_project_actual_nonlabor_unitsnumberBaseline actual nonlabor units
BL Remaining Nonlabor Unitsbl_project_remaining_nonlabor_unitsnumberBaseline remaining nonlabor units
Variance - BL Labor Unitsvariance_bl_project_labor_unitsnumberAt completion - baseline labor (negative = overrun)
Variance - BL Nonlabor Unitsvariance_bl_project_nonlabor_unitsnumberAt completion - baseline nonlabor (negative = overrun)

6. Costs (42 columns)

All cost fields including budgeted, actual, remaining, at-completion, baseline, and variance values.

Column NameIDData TypeDescription
Budgeted Costplanned_costcostTotal budgeted cost
Remaining Costremaining_costcostCost remaining to complete
Actual Costactual_costcostActual cost incurred
At Completion Costat_completion_costcostEstimate at completion (EAC)
Cost Variancecost_variancecostActual - Planned cost
Cost % Completecost_percent_completepercentActual / Planned cost
Planned Value (PV)planned_valuecostBCWS — Budgeted cost of work scheduled
Earned Value (EV)earned_valuecostBCWP — Budgeted cost of work performed
Cost Performance Indexcost_performance_indexnumberEV / AC (below 1 = over budget)
Actual Labor Costactual_labor_costcostActual labor cost incurred
Actual Nonlabor Costactual_nonlabor_costcostActual nonlabor cost incurred
Actual Material Costactual_material_costcostActual material cost incurred
Actual Expense Costactual_expense_costcostActual expense cost incurred
Actual Total Costactual_total_costcostTotal actual cost (all categories)
Actual This Period Labor Costactual_this_period_labor_costcostLabor cost in current period
Actual This Period Material Costactual_this_period_material_costcostMaterial cost in current period
Actual This Period Nonlabor Costactual_this_period_nonlabor_costcostNonlabor cost in current period
At Completion Labor Costat_completion_labor_costcostProjected total labor cost
At Completion Nonlabor Costat_completion_nonlabor_costcostProjected total nonlabor cost
At Completion Material Costat_completion_material_costcostProjected total material cost
At Completion Expense Costat_completion_expense_costcostProjected total expense cost
At Completion Total Costat_completion_total_costcostProjected total cost at completion
Budgeted Labor Costbudgeted_labor_costcostPlanned labor cost
Budgeted Nonlabor Costbudgeted_nonlabor_costcostPlanned nonlabor cost
Budgeted Material Costbudgeted_material_costcostPlanned material cost
Budgeted Expense Costbudgeted_expense_costcostPlanned expense cost
Budgeted Total Costbudgeted_total_costcostTotal planned cost
Remaining Labor Costremaining_labor_costcostRemaining labor cost
Remaining Nonlabor Costremaining_nonlabor_costcostRemaining nonlabor cost
Remaining Material Costremaining_material_costcostRemaining material cost
Remaining Expense Costremaining_expense_costcostRemaining expense cost
Remaining Total Costremaining_total_costcostTotal remaining cost
BL Labor Costbl_project_labor_costcostBaseline labor cost
BL Nonlabor Costbl_project_nonlabor_costcostBaseline nonlabor cost
BL Material Costbl_project_material_costcostBaseline material cost
BL Expense Costbl_project_expense_costcostBaseline expense cost
BL Total Costbl_project_total_costcostTotal baseline cost
Variance - BL Labor Costvariance_bl_project_labor_costcostAt completion - baseline labor cost
Variance - BL Nonlabor Costvariance_bl_project_nonlabor_costcostAt completion - baseline nonlabor cost
Variance - BL Material Costvariance_bl_project_material_costcostAt completion - baseline material cost
Variance - BL Expense Costvariance_bl_project_expense_costcostAt completion - baseline expense cost
Variance - BL Total Costvariance_bl_project_total_costcostAt completion - baseline total cost

7. Lists (8 columns)

Relationship and resource lookup fields.

Column NameIDData TypeDescription
PredecessorspredecessorsstringComma-separated predecessor activity IDs
SuccessorssuccessorsstringComma-separated successor activity IDs
Predecessor Detailspredecessor_detailsstringPredecessors with relationship type and lag
Successor Detailssuccessor_detailsstringSuccessors with relationship type and lag
Resource IDsresource_idsstringComma-separated resource identifiers
ResourcesresourcesstringComma-separated resource names
Role IDsrole_idsstringComma-separated role identifiers
RolesrolesstringComma-separated role names

8. Earned Value (42 columns)

Earned value management (EVM) metrics including BCWS, BCWP, CPI, SPI, variances, and forecasts.

Column NameIDData TypeDescription
Budget At Completionbudget_at_completioncostTotal baseline budget (BAC)
Planned Value Costplanned_value_costcostBCWS — Budgeted Cost of Work Scheduled
Earned Value Costearned_value_costcostBCWP — Budgeted Cost of Work Performed
Actual Cost (EV)actual_cost_evcostACWP — Actual Cost of Work Performed
BAC - Labor Unitsbudget_at_completion_labor_unitsnumberTotal baseline labor units
PV Labor Unitsplanned_value_labor_unitsnumberPlanned labor units to date
EV Labor Unitsearned_value_labor_unitsnumberEarned labor units based on progress
CPIcost_performance_index_evnumberEV / AC (below 1 = over budget)
CPI - Labor Unitscost_performance_index_labor_unitsnumberEV labor / actual labor units
SPIschedule_performance_index_evnumberEV / PV (below 1 = behind schedule)
SPI - Labor Unitsschedule_performance_index_labor_unitsnumberEV labor / PV labor units
CVcost_variance_evcostEV - AC (negative = over budget)
CV - Labor Unitscost_variance_labor_unitsnumberEV labor - actual labor units
CVIcost_variance_indexnumberCV / EV (% variance from budget)
CVI - Labor Unitscost_variance_index_labor_unitsnumberCV labor / EV labor
SVschedule_variance_evcostEV - PV (negative = behind schedule)
SV - Labor Unitsschedule_variance_labor_unitsnumberEV labor - PV labor units
SVIschedule_variance_indexnumberSV / PV (% variance from schedule)
SVI - Labor Unitsschedule_variance_index_labor_unitsnumberSV labor / PV labor
EAC Costestimate_at_completion_costcostProjected total cost
EAC - Labor Unitsestimate_at_completion_labor_unitsnumberProjected total labor units
ETCestimate_to_completecostExpected remaining cost
ETC Labor Unitsestimate_to_complete_labor_unitsnumberExpected remaining labor units
VACvariance_at_completioncostBAC - EAC (projected variance)
VAC - Labor Unitsvariance_at_completion_labor_unitsnumberBAC labor - EAC labor
TCPIto_complete_performance_indexnumber(BAC - EV) / (BAC - AC) — required future CPI
Accounting Varianceaccounting_variancecostCost accounting variance
Accounting Variance - Labor Unitsaccounting_variance_labor_unitsnumberLabor accounting variance
Performance % Completeperformance_percent_completepercent% complete for EV calculation
Performance % Complete - Laborperformance_percent_complete_labor_unitspercent% complete based on labor units
Schedule Varianceschedule_variancecostEV - PV
Schedule Performance Indexschedule_performance_indexnumberEV / PV
BCWSbcwscostBudgeted Cost of Work Scheduled
BCWPbcwpcostBudgeted Cost of Work Performed
SV (alias)svcostSchedule Variance (BCWP - BCWS)
CV (alias)cvcostCost Variance (BCWP - ACWP)
SPI (alias)spinumberSchedule Performance Index
CPI (alias)cpinumberCost Performance Index
EAC (alias)eaccostEstimate at Completion
ETC (alias)etccostEstimate to Complete
VAC (alias)vaccostVariance at Completion
TCPI (alias)tcpinumberTo Complete Performance Index

9. Enhanced Metrics (21 columns)

Calculated and derived metrics computed by Kazinex from raw data.

Column NameIDData TypeDescription
At Completion Labor Unitsat_completion_labor_unitsnumberProjected total work hours
At Completion Nonlabor Unitsat_completion_nonlabor_unitsnumberProjected total nonlabor units
Activity % Completeactivity_percent_completepercentOverall % based on configured type
Cost % of Budgetcost_pct_of_budgetpercentActual / budgeted cost
Duration % of Originalduration_pct_of_originalpercentAt completion / original duration
Schedule % Completeschedule_pct_completepercentTime-based schedule completion
Hard Constrainthas_hard_constraintbooleanHas constraining date restriction
Is Milestoneis_milestonebooleanActivity is a milestone
Criticalitycriticality_statusstringCritical, Near-Critical, or Normal
Critical Pathcritical_path_indicatorstringCritical, Near-Critical, or Non-Critical
Has Constraintshas_constraintsbooleanHas hard constraints applied
Labor Hourslabor_hoursnumberTotal labor hours assigned
Equipment Hoursequipment_hoursnumberTotal equipment hours assigned
Material Costmaterial_costcostTotal material cost
Total Resource Costtotal_resource_costcostSum of all resource costs
Resource CountresourceCountnumberNumber of resources assigned
OverallocatedoverallocatedbooleanAny resource overallocated
Peak Loading %peak_loadingpercentPeak resource loading percentage
Average Loading %average_loadingpercentAverage resource loading percentage
WBS Codewbs_codestringWork Breakdown Structure code
WBS Namewbs_namestringWork Breakdown Structure name

10. Number of Activities (11 columns)

Activity count fields used primarily in grouped/summary rows.

Column NameIDData TypeDescription
Activity Countactivity_countnumberCount of activities in group
Resource Assignment Countactivity_resource_assignment_countnumberCount of resource assignments
Actual Completedactual_completed_activitiesnumberActivities with actual finish
Actual In-Progressactual_in_progress_activitiesnumberActivities started but not finished
Actual Not-Startedactual_not_started_activitiesnumberActivities without actual start
BL Completedbl_project_completed_activitiesnumberShould be completed per baseline
BL In-Progressbl_project_in_progress_activitiesnumberShould be in-progress per baseline
BL Not-Startedbl_project_not_started_activitiesnumberShould not be started per baseline
Variance - Completedvariance_completed_activitiesnumberActual - BL completed (positive = ahead)
Variance - In-Progressvariance_in_progress_activitiesnumberActual - BL in-progress
Variance - Not-Startedvariance_not_started_activitiesnumberActual - BL not-started

11. Activity Codes (Dynamic)

Activity code columns are created dynamically based on the codes defined in your uploaded file. Common P6 activity code types include:

  • Area — Geographic or site area
  • Phase — Project phase (Design, Procurement, Construction, etc.)
  • Responsibility — Team or person responsible
  • Discipline — Engineering discipline (Civil, Mechanical, Electrical, etc.)

Each activity code type becomes a column in the grid showing the assigned code value per activity.


12. User Defined Fields (Dynamic)

UDF columns are created from the User Defined Field definitions in your file. UDFs can be of types: Text, Number, Integer, Date, Start Date, Finish Date, Cost, or Indicator.


13. Predecessors / Successors (Dynamic)

Relationship detail columns are generated from the logic data, showing predecessor and successor information with relationship types and lag values.


Summary

Category# ColumnsData Types Used
General20string, number, date, boolean
Dates33date, string
Durations26duration, number, boolean, string
Percent Complete43percent, string
Units17number
Costs42cost, percent, number
Lists8string
Earned Value42cost, number, percent
Enhanced Metrics21number, percent, boolean, string, cost
Number of Activities11number
Activity CodesDynamicstring
User Defined FieldsDynamicvaries
Predecessors/SuccessorsDynamicstring
Total265+