Skip to main content

Gantt Context Menu

Available in: All plans
Last updated: 06-Mar-2026

Overview​

Right-clicking a Gantt bar or the chart background opens a context menu with quick actions. The menu adapts based on what you click — a task bar, a milestone, a summary bar, empty space, or a dependency line.

Gantt bar right-click menu — View Details, Show Critical Path, Zoom to Fit This BarGantt bar right-click menu — View Details, Show Critical Path, Zoom to Fit This Bar

Bar Context Menu​

Right-click any activity bar to see these options:

ActionShortcutDescription
Scroll to Activity—Centres the grid on this activity's row
Activity DetailsEnterOpens the Activity Details side panel for this activity
Edit Start Date—Opens the date picker pre-filled with the current early start
Edit Finish Date—Opens the date picker pre-filled with the current early finish
Edit Duration—Opens the duration editor for original or remaining duration
Add Relationship—Starts interactive relationship drawing from this activity
Set Constraint—Opens the constraint picker (Must Start On, SNET, FNLT, etc.)
Mark as Critical—Toggles a manual critical-path override flag
Copy Activity IDCtrl+CCopies the activity ID to the clipboard
Delete ActivityDelRemoves the activity (with confirmation)

Milestone-Specific Options​

When you right-click a milestone diamond, the menu adds:

ActionDescription
Toggle Start/FinishSwitch between start milestone and finish milestone type
Edit Milestone DateOpens a single date picker for the milestone date

Summary Bar Options​

Right-clicking a WBS summary bar shows:

ActionDescription
Expand All ChildrenExpands every nested WBS level beneath this node
Collapse All ChildrenCollapses all child rows under this summary
Select All ActivitiesSelects every activity within this WBS scope

Background Context Menu​

Right-click an empty area of the Gantt chart (not on a bar) to see:

ActionDescription
Zoom to FitAutomatically scales the time axis to fit all visible activities
Zoom to SelectionZooms to the date range of the currently selected activities
Zoom to Data DateCentres the view on the schedule's data date
Go to DateOpens a date picker to jump the Gantt to any date
Show/Hide Data Date LineToggles the data date marker line
Show/Hide Baseline BarsToggles primary baseline bar visibility
Gantt SettingsOpens the full Gantt Settings panel

Dependency Line Context Menu​

Right-click a relationship line between two bars:

ActionDescription
Edit RelationshipOpens the relationship editor with type and lag fields
Delete RelationshipRemoves the predecessor/successor link (with confirmation)
Show PredecessorScrolls to and highlights the predecessor activity
Show SuccessorScrolls to and highlights the successor activity

Keyboard Alternative​

You can also trigger the context menu from the keyboard:

  1. Select an activity row in the grid.
  2. Press Shift+F10 (or the Menu key) to open the context menu at the selected bar's position.

Tips​

Quick navigation

Use Scroll to Activity from the Gantt context menu when you have found an activity in the grid and want to see its bar position on the timeline.

Bulk operations

Select multiple activities in the grid first, then right-click any selected bar. Bulk-applicable actions (Delete, Set Constraint) will apply to the entire selection.