Work Package Lifecycle

Work packages move through a defined lifecycle as the work progresses. This guide explains each status, the transitions between them, and who can trigger each transition.

Status overview

Open → In Progress → Submitted → Approved → Closed

(Returned)
StatusColourMeaning
OpenGreyCreated but work has not started
In ProgressBlueWork is actively being done
SubmittedAmberAssignee has marked it ready for review
ReturnedOrangeReviewer sent it back with comments
ApprovedGreenAll required workflows completed; package accepted
ClosedDark greyPackage closed — permanently archived

Status transitions

Open → In Progress

Who: Assigned member (or Project Admin)
When: Work on the package begins
How: Open the work package → click Mark as In Progress

Use this transition to signal that work has started. It starts the clock for overdue tracking against the due date.

In Progress → Submitted

Who: Assigned member (or Project Admin)
When: All documents in the package have been delivered and are ready for review/acceptance
How: Open the work package → click Submit
Prerequisite check: The system may check whether linked workflows are complete before allowing submission (depends on your project configuration). If workflows are still active, you see a warning.

Submitted → Returned

Who: Project Admin (or designated reviewer)
When: Submission is incomplete — documents missing, workflows not complete, quality issue
How: Open the work package → click Return → add a note explaining what's needed
Effect: Status returns to In Progress. Assigned member is notified with the return reason.

Submitted → Approved

Who: Project Admin (or designated reviewer)
When: All documents are accepted; linked workflows are complete; package meets the deliverable requirement
How: Open the work package → click Approve

Approved → Closed

Who: Project Admin
When: End of project, or formal close-out after all close-out evidence is attached
How: Open the work package → click Close
Effect: Status changes to Closed. The package is read-only — no further edits, documents, or workflows can be added.

Adding close-out evidence

Before closing a work package, attach any close-out evidence:

  1. Open the work package.
  2. Click Add Document → select the signed-off inspection record, test certificate, or close-out report.
  3. The close-out document appears in the Documents list.
  4. Then click Close.

Overdue tracking

A work package is overdue when:

  • Status is Open or In Progress, AND
  • The current date is past the Due Date

Overdue packages show in red in the Work Packages list and appear in the Dashboard overdue alerts panel.