Project Roles

Available in: All tiers
Last updated: 05-Mar-2026

Overview​

Every uploaded schedule in Kazinex can be assigned a role that determines how it is used across the application. Roles affect quality checks, schedule comparison, AI Copilot context, and dashboard metrics.

Role Types​

RoleBadge ColourPurpose
CurrentBlueThe active working schedule — used as the primary data source for quality checks, the Activities grid, Gantt chart, and AI Copilot
BaselineGreenThe approved reference schedule — used as the comparison target for variance analysis and baseline comparison features
ArchivedGreyOlder schedule versions kept for historical reference — excluded from dashboard metrics
NoneNo badgeNewly uploaded schedules that have not been assigned a role yet

Only one project can be marked as Current and one as Baseline at any time within a workspace.


Assigning Roles​

From the Projects Tab​

  1. Navigate to the Projects tab
  2. Find the project you want to assign
  3. Right-click (or click the ⋮ menu) → select Mark as Current or Mark as Baseline
  4. The previous holder of that role is automatically demoted to None

From the Import Wizard​

During upload, the Import Wizard offers a checkbox to immediately mark the new schedule as Current or Baseline.

Quick Switch​

Click the role badge on any project card to cycle through available roles: None → Current → Baseline → Archived → None.


How Roles Affect Features​

Quality Checks​

FeatureCurrentBaselineArchivedNone
Quality score displayed✓✓——
Included in portfolio average✓———
Progress checks available✓———

Schedule Comparison​

The Comparison tab uses Current and Baseline as the default pair:

  • Left side (Current): The working schedule showing the latest status
  • Right side (Baseline): The approved reference for variance calculation

You can override this default by manually selecting any two projects in the comparison selector.

AI Copilot​

The AI Copilot uses the Current project as its primary context. When you ask questions or request modifications, the Copilot reads from and writes to the Current schedule. If a Baseline is set, the Copilot can also reference it for comparison-based questions.

Dashboard & Portfolio​

Only projects marked as Current contribute to the Portfolio Overview KPIs (on-track rate, average quality score, schedule health).


Role Change History​

Every role change is logged in the Change History panel:

FieldValue
ActionRole Changed
FromPrevious role (e.g., None)
ToNew role (e.g., Current)
ByUser who made the change
TimestampWhen the change occurred

Best Practices​

tip
  • Always set a Baseline before beginning progress updates — this ensures comparison features show meaningful variances.
  • Archive old schedules rather than deleting them so you retain a full audit trail.
  • Mark Current immediately after uploading a new update so that the dashboard, quality checks, and AI Copilot all reflect the latest data.