Quality Check Reference

Last updated: 05-Mar-2026

This page provides a single-table reference of every quality check available in Kazinex. For detailed explanations, threshold configuration, and remediation guidance, click through to the individual check pages.


Check Categories at a Glance​

CategoryChecksPage
Logic8Logic Checks
Duration7Duration Checks
Constraints4Constraint Checks
Critical Path2Critical Path Checks
Resources2Resource Checks
Progress2Progress Checks
Configuration5Configuration Checks
Best Practice4Best Practice Checks
Regional2Regional Checks

Complete Check Table​

Logic Checks​

CheckDefault ThresholdSeverityDescription
Missing Logic> 5% of activitiesHighActivities with no predecessors or no successors
Negative FloatAny activityCriticalActivities with negative total float indicating schedule overrun
High Float> 44 working days TFMediumUnusually high total float suggesting missing logic
LeadsAny lead presentMediumNegative lag on relationships (leads)
Lags> 5% of relationshipsMediumPositive lag on relationships
Negative LagAny negative lagHighNegative lag values that can cause calculation issues
FS Relationships< 90% FSLowFinish-to-Start relationships as a percentage of total
Hard Constraints> 5% of activitiesMediumMandatory constraints that override CPM logic

Duration Checks​

CheckDefault ThresholdSeverityDescription
High Duration> 44 working daysMediumActivities with original duration exceeding threshold
Zero DurationAny task with OD = 0MediumNon-milestone tasks with zero original duration
Milestone DurationMilestone with OD > 0LowMilestones that have a non-zero duration
Invalid DatesAny occurrenceHighActivities with illogical date combinations
Level of Effort> 10% of activitiesLowLOE activities as percentage of total
Approval Duration> 20 working daysMediumApproval-type activities with excessive duration

Constraint Checks​

CheckDefault ThresholdSeverityDescription
Constraint Percentage> 5% of activitiesMediumActivities with date constraints
Dangling ActivitiesAny occurrenceHighActivities with neither predecessors nor successors
Open EndedAny occurrenceHighActivities missing either a predecessor or successor
Start-Finish RelationshipsAny SF relationshipMediumStart-to-Finish relationships (unusual and often erroneous)

Critical Path Checks​

CheckDefault ThresholdSeverityDescription
CPLI (Critical Path Length Index)< 1.0HighRatio of critical path length to project duration — below 1.0 signals overrun risk
BEI (Baseline Execution Index)< 1.0HighRatio of planned progress to actual progress along the critical path

Resource Checks​

CheckDefault ThresholdSeverityDescription
Missing Resources> 20% unassignedMediumPercentage of activities without resource assignments
Resource LoadingOver-allocation detectedMediumResources assigned beyond their maximum availability

Progress Checks​

CheckDefault ThresholdSeverityDescription
Invalid ProgressAny occurrenceHighActivities with contradictory progress data (e.g., actual start but 0% complete)
Out-of-SequenceAny occurrenceMediumActivities progressing before their predecessors are complete

Configuration Checks​

CheckDefault ThresholdSeverityDescription
Activity TypeNon-standard types > 10%LowActivities not using Task Dependent type
Percent Complete TypeNon-standard types > 10%LowActivities not using Duration-based percent complete
Duration TypeNon-standard types > 10%LowActivities not using Fixed Duration & Units
Constraint TypeHard constraints > 5%MediumActivities using mandatory constraint types
Secondary ConstraintAny secondary constraintLowActivities with secondary constraints applied

Best Practice Checks​

CheckDefault ThresholdSeverityDescription
Logic Density< 1.5 relationships/activityMediumAverage number of relationships per activity
Baseline IntegrityBaseline missingHighWhether a baseline schedule is set and aligned
Project Milestones< 2 milestonesLowMinimum number of key milestones expected
Weightage DistributionUneven distributionLowHow evenly weights are spread across check categories (opt-in)

Regional Checks​

CheckDefault ThresholdSeverityDescription
Ramadan CalendarCalendar not adjustedMediumWhether project calendars account for Ramadan working hour changes
Authority Approval MilestonesMissing approvalsMediumWhether required authority approval milestones are present

Severity Levels​

LevelColourImpact
CriticalRedDirect schedule integrity risk — must be resolved
HighOrangeSignificant quality concern — resolve before submission
MediumAmberModerate concern — review and address when possible
LowBlueInformational — consider for best practice compliance

Threshold Customisation​

All thresholds can be customised per-workspace in Quality Settings. Changes apply to all subsequent quality check runs. The Weightage Configuration page explains how to adjust the scoring weight of each check category.