Portfolio Overview

Available in: Pro · Enterprise
Last updated: 05-Mar-2026

Overview

The Portfolio Overview provides a high-level dashboard of all projects in your workspace. It aggregates key performance indicators, quality scores, and schedule health metrics so you can spot issues without drilling into individual projects.

Access the portfolio overview from the Portfolio Pulse hero section at the top of the Projects tab.

Portfolio KPIs

The hero section displays real-time metrics drawn from your current and baseline schedules:

KPIDescription
Total ProjectsCount of all uploaded schedules in the workspace
Active ProjectsProjects marked as Current (not archived)
Average Quality ScoreWeighted average of all current projects' quality scores
Schedule HealthPercentage of projects with a quality score above 70%
On-Track RatePercentage of projects where forecast finish ≤ baseline finish

KPIs update automatically when you upload new schedules or recalculate quality checks.


Visual Indicators

Status Badges

Each project in the portfolio is tagged with a colour-coded badge:

BadgeColourMeaning
CurrentBlueThe active working schedule
BaselineGreenThe approved baseline schedule
ArchivedGreyOlder versions kept for reference
NoneNo badgeNot yet assigned a role

Quality Score Ring

Each project card includes a circular progress indicator showing its quality score:

Score RangeColourInterpretation
80–100%GreenHealthy schedule
60–79%AmberNeeds attention
0–59%RedSignificant issues

Sorting and Grouping

Sort Options

Sort the portfolio view by:

FieldDirectionDefault
Project NameA–Z / Z–A
Upload DateNewest / OldestNewest first ✓
Quality ScoreHighest / Lowest
Activity CountMost / Fewest
Data DateLatest / Earliest

Group By

Group projects by:

  • Status — Current, Baseline, Archived
  • Quality Band — Green / Amber / Red
  • Upload Month — Grouped by the month uploaded
  • None — Flat list (default)

Portfolio-Level Actions

From the portfolio overview you can:

ActionHow
Bulk importUpload multiple XER/XML files at once — see Bulk Import
Mark Current / BaselineRight-click a project → change its role — see Current & Baseline Marking
Delete projectsSelect one or more projects → Delete
Export summaryDownload a CSV of all project KPIs via the Export button

Refresh Behaviour

The portfolio overview refreshes when:

  1. A new schedule is uploaded or deleted
  2. A quality check completes
  3. A project's role (Current/Baseline) changes
  4. You manually click the Refresh button in the toolbar

Metric calculations run client-side for instant feedback — no server round-trip required.

tip

Pin the projects with the lowest quality scores to the top by sorting Quality Score → Lowest first. This keeps problem schedules visible so they don't slip through review cycles.