Overview

Every uploaded schedule in Kazinex can be assigned a role that determines how it is used across the application. Roles affect quality checks, schedule comparison, AI Copilot context, and dashboard metrics.

Role Types

RoleBadge ColourPurpose
CurrentBlueThe active working schedule — used as the primary data source for quality checks, the Activities grid, Gantt chart, and AI Copilot
BaselineGreenThe approved reference schedule — used as the comparison target for variance analysis and baseline comparison features
ArchivedGreyOlder schedule versions kept for historical reference — excluded from dashboard metrics
NoneNo badgeNewly uploaded schedules that have not been assigned a role yet

Only one project can be marked as Current and one as Baseline at any time within a workspace.


Assigning Roles

From the Projects Tab

  1. Navigate to the Projects tab
  2. Find the project you want to assign
  3. Right-click (or click the menu) → select Mark as Current or Mark as Baseline
  4. The previous holder of that role is automatically demoted to None

From the Import Wizard

During upload, the Import Wizard offers a checkbox to immediately mark the new schedule as Current or Baseline.

Quick Switch

Click the role badge on any project card to cycle through available roles: None → Current → Baseline → Archived → None.


How Roles Affect Features

Quality Checks

FeatureCurrentBaselineArchivedNone
Quality score displayed
Included in portfolio average
Progress checks available

Schedule Comparison

The Comparison tab uses Current and Baseline as the default pair:

  • Left side (Current): The working schedule showing the latest status
  • Right side (Baseline): The approved reference for variance calculation

You can override this default by manually selecting any two projects in the comparison selector.

AI Copilot

The AI Copilot uses the Current project as its primary context. When you ask questions or request modifications, the Copilot reads from and writes to the Current schedule. If a Baseline is set, the Copilot can also reference it for comparison-based questions.

Dashboard & Portfolio

Only projects marked as Current contribute to the Portfolio Overview KPIs (on-track rate, average quality score, schedule health).


Role Change History

Every role change is logged in the Change History panel:

FieldValue
ActionRole Changed
FromPrevious role (e.g., None)
ToNew role (e.g., Current)
ByUser who made the change
TimestampWhen the change occurred

Best Practices

tip
  • Always set a Baseline before beginning progress updates — this ensures comparison features show meaningful variances.
  • Archive old schedules rather than deleting them so you retain a full audit trail.
  • Mark Current immediately after uploading a new update so that the dashboard, quality checks, and AI Copilot all reflect the latest data.