Overview​

Grouping lets you organise activities into a collapsible hierarchy β€” by WBS level, activity status, activity codes, resources, or any other field. Group headers display aggregated values (sums, averages, counts) so you can analyze your schedule at any level of detail.

Open the Grouping dialog by clicking Grouping in the Activities Grid toolbar.

Grouping dialog β€” group activities by WBS, codes, or fieldsGrouping dialog β€” group activities by WBS, codes, or fields

The Grouping Dialog​

The dialog opens as a wide modal (Configure Grouping) with three main areas:

AreaWidthPurpose
Available Fields (left)35%Browse fields grouped by category, with search
Grouping Levels (centre)45%Your selected grouping levels in priority order
Preview (right)20%Live preview of the resulting hierarchy

An Options section appears below the three columns.

On tablet, the preview stacks below the two main columns. On mobile, all sections stack vertically in a single column.

Adding Grouping Levels​

  1. In the Available Fields panel, browse categories or type in the search bar to find a field.
  2. Click a field to add it as the next grouping level.
  3. Repeat to add up to 7 levels (maximum).

Fields are organized into 10 categories in collapsible accordion sections: General, Dates, Durations, Percent Complete, Costs, Units, Activity Codes, Lists, User Defined Fields, and more.

Reordering Levels​

Grouping levels are applied in order β€” Level 1 is the outermost group, Level 2 nests inside it, and so on.

  • Drag and drop the numbered level cards to rearrange them.
  • Each card shows a numbered badge (1, 2, 3…) indicating its position in the hierarchy.

Removing Levels​

Click the remove (βœ•) button on any level card to delete it. Or click Clear Grouping in the footer to remove all levels at once.

Built-in Templates​

The dialog offers three one-click templates to get you started quickly:

TemplateLevelsBest For
WBS HierarchyWBS Level 1 β†’ Level 2 β†’ Level 3Standard P6-style WBS breakdown
Phase & StatusPhase (Activity Code) β†’ StatusTracking progress by project phase
Resource AllocationResource β†’ WBS Level 1Seeing which resources work on which WBS elements

Click a template to replace your current grouping configuration with the template's levels.

WBS Level Selector​

When you add a WBS field as a grouping level, a special WBS Level Selector appears on that level's card:

  • Choose Level 1 through Level N (where N is the deepest WBS level in your schedule).
  • Choose All Levels (Full Hierarchy) to display the complete WBS tree.
  • A helper label shows: "Maximum level in this XER: Level N".

The same level selector appears for hierarchical Activity Codes (e.g., Phase β†’ Sub-Phase) when the code type has multiple depth levels.

Live Preview​

The right panel updates in real time (with a 450 ms debounce) to show a mock tree of your grouping hierarchy using actual data from the loaded schedule. Each preview node shows:

  • An expand/collapse chevron
  • The group label
  • An activity count badge

Click nodes in the preview to expand or collapse them. The preview renders up to 3 levels deep and samples up to 15 activities.

Options​

Three checkboxes appear in the Options section below the columns:

OptionDefaultDescription
Show empty groupsOffDisplay group headers even if they contain zero activities after filtering.
Show summariesOnDisplay aggregated values (sum, average, min, max) in group header rows.
Collapse allOffStart with all groups collapsed after applying.

Row Model Modes​

When you add your first grouping level, the dialog detects the appropriate row model mode automatically:

ModeWhen UsedDescription
DefaultFirst level is not WBS or Activity CodeStandard flat grouping with basic aggregation.
WBS CustomFirst level is a WBS fieldHierarchical tree with proper parent–child nesting, WBS-specific aggregations, and depth-based indentation.
Activity Code CustomFirst level is an Activity CodeHierarchical tree for multi-level activity codes with parent–child nesting.

You can also manually select a row model mode using the mode selector at the top of the dialog.

Working with Groups in the Grid​

Once grouping is applied:

  • Click a chevron to expand or collapse a single group.
  • Shift+Click a chevron to expand or collapse a group and all its descendants.
  • Ctrl+Shift+E expands all groups.
  • Ctrl+Shift+C collapses all groups.
  • Right-click a group header for Expand All, Collapse All, Expand This, or Collapse This.

Group headers display inline aggregated values in each column (sums for cost/duration fields, averages for percentages, counts for activity counts). When Show summaries is enabled, dedicated summary rows may appear below each group with additional rollup data.

Large-Tree Performance​

When expanding a large hierarchy (500+ nodes), Kazinex processes the expansion in batches (100 nodes per frame) with a progress bar so the UI stays responsive.

Applying or Clearing​

  • Click Apply Grouping to save your configuration and close the dialog.
  • Click Cancel to discard changes.
  • Click Clear Grouping in the footer to remove all grouping and return to a flat activity list.