Progress Checks
Category weight: 10% of overall score
Checks in this category: 2
Progress checks verify that progress data is consistent and follows the schedule logic. Invalid progress data corrupts earned value calculations, and out-of-sequence progress indicates that work is happening in a different order than planned.
Invalid Progress
| Field | Value |
|---|---|
| Check ID | invalid-progress |
| DCMA Reference | Point 12 |
| Default Threshold | No invalid percent complete values |
| Severity | Major |
Detects activities with logically impossible percent complete values.
What triggers a finding:
- Physical percent complete is less than 0%
- Physical percent complete is greater than 100%
- Physical percent complete is 100% but the activity has no actual finish date
- Physical percent complete is < 100% but the activity has an actual finish date
Why it matters: Invalid progress data makes earned value metrics unreliable. A 100%-complete activity without an actual finish date will be counted as complete in EV metrics but will still consume float in the CPM calculation.
Out-of-Sequence Progress
| Field | Value |
|---|---|
| Check ID | out-of-sequence-progress |
| DCMA Reference | Point 12 |
| Default Threshold | No out-of-sequence violations |
| Severity | Major |
Detects activities that have started or progressed before their predecessors allow. This means work is happening in a different order than the schedule logic dictates.
What triggers a finding: An activity has actual progress, but one or more of its predecessor relationships have not been satisfied:
| Relationship | Violation Condition |
|---|---|
| FS (Finish-to-Start) | Successor started before predecessor finished (accounting for lag) |
| SS (Start-to-Start) | Successor started before predecessor started (accounting for lag) |
| FF (Finish-to-Finish) | Successor finished before predecessor finished (accounting for lag) |
| SF (Start-to-Finish) | Successor finished before predecessor started (accounting for lag) |
Why it matters: Out-of-sequence progress indicates one of two things:
- The relationships are wrong — the logic should be updated to reflect the actual execution sequence.
- Work started prematurely — the team is not following the planned sequence, which can create schedule risk.
Either way, the schedule planner should investigate and correct the issue.