Resource Checks

Category weight: 10% of overall score
Checks in this category: 2

Resource checks verify that activities have appropriate resource assignments and that resource loading is consistent. A schedule without resources cannot support earned value analysis or resource levelling.

Missing Resources

FieldValue
Check IDmissing-resources
DCMA ReferencePoint 10
Default Threshold≥ 95% of activities should have at least one resource assignment
SeverityMinor

Detects activities that have no resource assignments — no labour, equipment, or material resources are allocated.

What triggers a finding: An activity with zero resource assignments.

Exceptions: Milestones and Level of Effort activities may legitimately have no resources. The threshold accommodates a small percentage of unresourced activities.

Why it matters: Activities without resources cannot be included in resource histograms, S-curves, or earned value calculations. If your organization uses resource loading for reporting, gaps in resource assignments create blind spots.


Resource Loading

FieldValue
Check IDresource-loading
DCMA ReferencePoint 10
Default Threshold8-aspect validation suite
SeverityMinor

A comprehensive resource validation that checks multiple aspects of resource data quality:

AspectWhat It Checks
CostActivities have budgeted costs assigned
Progress UnitsActual units align with percent complete
LabourLabour resource assignments exist and have unit values
EquipmentEquipment resources, where assigned, have valid data
MaterialMaterial resources, where assigned, have valid quantities
CalendarsResource calendars are assigned and valid
AvailabilityResource availability limits are defined
BalanceResource loading is reasonably balanced across the schedule

What triggers a finding: Any of the 8 aspects fails its individual validation criteria.

Why it matters: Partial resource data is often worse than no resource data — it can produce misleading earned value metrics and incorrect resource forecasts.