Edit a Schedule — Full Walkthrough
Time: ~25 minutes Level: Intermediate Applies to: Pro · Enterprise
What You Will Learn
By the end of this tutorial, you will be able to:
- Add activities and edit their properties inline
- Use the WBS Editor to restructure your breakdown
- Create and customise calendars with exceptions
- Create different relationship types (FS, SS, FF)
- Add resources and assign them to activities
- Create activity codes and assign values
- Create a User Defined Field (UDF)
- Run the CPM calculation and review results
- Undo and redo changes
Prerequisites
- A Kazinex account on the Pro or Enterprise tier
- A schedule open in Editor mode (see Create a Schedule from Scratch)
Step 1 — Add New Activities
Add activities directly in the grid using inline editing.
- Navigate to a WBS node where you want to add activities.
- Click the + (Add Activity) button at the bottom of the WBS group.
- Type the activity name (for example, "Rebar Installation") and press Tab.
- Enter the duration (for example, "12d") and press Enter.
- Add two more activities: "Formwork Erection" (8d) and "Concrete Pour" (3d).
What you should see: Three new activity rows appear in the grid under the selected WBS node. Each shows the name, duration, and a blank bar in the Gantt.
Step 2 — Edit Activity Properties
Change an activity's properties using inline cell editing.
- Double-click on the Duration cell of "Formwork Erection".
- Change it from 8d to 10d and press Enter.
- Click on the Constraint cell for "Concrete Pour".
- Select Start On or After from the dropdown and set a constraint date.
- Click on the Calendar cell and assign a specific calendar if needed.
What you should see: The grid cells update immediately. The Gantt bar adjusts its length and position to reflect the new duration and constraint.
Step 3 — Restructure the WBS
Use the WBS Editor to add, rename, and move WBS nodes.
- Open the WBS Editor from the toolbar or the Editor panel.
- Right-click on an existing WBS node and select Add Child Node.
- Name the new node (for example, "External Works").
- Right-click on the new node and select Rename to change its name.
- Drag an existing activity from one WBS node to the new "External Works" node.
What you should see: The WBS tree updates with the new node. Activities under the moved node re-group in the grid.
Step 4 — Create a Custom Calendar
Build a calendar with different work patterns and holiday exceptions.
- Open the Calendar Editor from the toolbar.
- Click Add Calendar and name it "6-Day Calendar".
- Toggle work days to Monday through Saturday (6 days).
- Set work hours to 07:00–16:00 with a 30-minute lunch break.
- Click Add Exception and enter a bank holiday (for example, "Eid Al Fitr — 30-Mar-2027").
- Click Save.
What you should see: The calendar appears in the calendar list. You can now assign it to activities that follow a 6-day work pattern.
Step 5 — Create Different Relationship Types
Build your network with FS, SS, and FF relationships.
- Open the Relationship Editor from the toolbar.
- Create a Finish-to-Start (FS) relationship: "Rebar Installation" → "Formwork Erection".
- Create a Start-to-Start (SS) relationship: "Formwork Erection" → "Concrete Pour" with a lag of 5d (concrete starts 5 days after formwork begins).
- Create a Finish-to-Finish (FF) relationship between two parallel activities if applicable.
- Review the relationship list to confirm all three types exist.
What you should see: Dependency arrows in the Gantt reflect each relationship type. SS and FF relationships display different arrow shapes compared to FS.
Step 6 — Add and Assign Resources
Attach labour, equipment, or material resources to activities.
- Open the Resource Editor from the toolbar.
- Click Add Resource and create a Labour resource named "Carpenter" with a max units of 4.
- Create a second resource: Equipment named "Tower Crane" with max units of 1.
- Close the Resource Editor.
- Select the activity "Formwork Erection" in the grid.
- In the activity detail panel, click Assign Resource and select "Carpenter" with 2 units.
- Assign "Tower Crane" to "Concrete Pour" with 1 unit.
What you should see: The resource assignments appear in the activity detail panel. If you add the Resources columns to the grid, you see resource names and unit counts.
Step 7 — Create Activity Codes
Organise activities using activity code types and values.
- Open the Activity Code Editor from the toolbar.
- Click Add Activity Code Type and name it "Phase".
- Add values under the "Phase" type: "Design", "Construction", "Commissioning".
- Close the editor.
- Select multiple activities in the grid.
- Assign the activity code "Phase = Construction" to them using the activity detail panel or bulk edit.
What you should see: Activities now have a "Phase" attribute. You can group or filter the grid by Phase to see activities categorised by construction phase.
Step 8 — Create a User Defined Field
Add custom data fields to capture project-specific information.
- Open the UDF Editor from the toolbar.
- Click Add UDF and create a text field named "Contractor".
- Set the UDF type to Text.
- Close the editor.
- Add the "Contractor" column to the grid using the Column Chooser.
- Double-click a cell in the Contractor column and enter a value (for example, "ABC Building Co.").
What you should see: The custom "Contractor" column appears in the grid. You can enter free text values for each activity.
Step 9 — Run the CPM Calculation
Recalculate the schedule with all your changes applied.
- Click the Calculate button in the toolbar (or press F9).
- Wait for the CPM engine to complete.
- Review the Calculation Results panel for any warnings or errors.
- Common warnings include: open-ended activities, negative float, or calendar conflicts.
What you should see: All activities update with new Early Start, Early Finish, Late Start, Late Finish, and Total Float values. The Gantt redraws with updated bar positions.
Step 10 — Use Undo and Redo
Every change in the Editor can be reversed.
- Press Ctrl+Z to undo the last change.
- Notice the activity reverts to its previous state.
- Press Ctrl+Y (or Ctrl+Shift+Z) to redo the change.
- You can undo multiple times to step back through your edit history.
What you should see: Each undo step reverses one change. The grid and Gantt update in real-time. The undo stack is maintained for the entire editing session.
Step 11 — Verify Your Work
Confirm you have used all the major Editor features.
- The grid shows activities with edited durations and constraints.
- The WBS tree has a new node ("External Works") with activities assigned.
- A custom "6-Day Calendar" exists in the calendar list.
- Relationships of types FS, SS, and FF are visible in the Gantt.
- Resources ("Carpenter", "Tower Crane") are assigned to activities.
- Activity codes ("Phase") are assigned to multiple activities.
- A UDF column ("Contractor") is visible in the grid with values entered.
- The CPM calculation has run successfully.
What you should see: A fully edited schedule demonstrating proficiency with every Editor component.
What's Next?
- Compare Two Schedule Periods — bookmark this schedule and compare it against a future update
- Achieve a 90+ Quality Score — run quality checks on your schedule
- Editor Reference — detailed documentation for each Editor panel
Troubleshooting
| Issue | Solution |
|---|---|
| Cannot add activities | Make sure you are in Editor mode. View-only mode does not allow adding activities. |
| Relationship Editor does not show activity | The activity must exist and be saved before it can be used in a relationship. |
| Calendar changes not reflected in dates | Run the CPM calculation (F9) after changing calendars. Dates update only after recalculation. |
| UDF column not visible | Open the Column Chooser and search for your UDF name. UDFs appear in the "User Defined" category. |
| Undo not working | Undo only works within the current editing session. Changes saved before this session cannot be undone. |
| Resource over-allocation warning | Check that assigned units do not exceed the resource's max units. Reduce assignments or increase the max. |