Resource Usage Profile Component

The Resource Usage Profile component renders time-phased resource data as histograms, area charts, or stacked bars, showing how resources are planned, allocated, or consumed over a project period. It is the primary reporting component for workforce planning, capacity management, and resource cost reporting.

Presets

PresetDescription
Periodic loadingResource hours or units per period as a bar chart.
Cumulative loadingRunning total of resource consumption as an area chart.
Baseline vs. ActualTwo bar series comparing planned loading to actual loading per period.
Cost profileResource cost per period as bars with a cumulative cost line overlay.
Allocation by roleStacked bars showing each role's contribution to the total per period.
Capacity vs. demandResource demand bars with a capacity reference line.
ExecutiveSingle cumulative line with KPI summary cards above the chart.

Data binding

PropertyDescription
Period fieldTime axis (week, fortnight, month, quarter).
Resource value fieldThe primary numeric measure to chart (hours, units, cost, or allocation %).
Group by fieldOptional field to split the value into stacked or grouped series (e.g., role, discipline, contractor).
Baseline fieldOptional planned/baseline value for comparison.
Capacity fieldOptional capacity limit per period for overload detection.

Measurement modes

ModeDescription
UnitsPhysical quantity of the resource (e.g., number of workers per day).
HoursLabour hours per period.
CostResource cost per period.
Allocation %Percentage of available capacity used.

Stack-by options

When a Group by field is configured, the chart can be displayed as:

ModeDescription
StackedAll groups stacked to show total demand with composition.
Grouped (side by side)Each group as a separate bar per period for direct comparison.
100% stackedEach period normalised to 100% showing group proportions.
Series linesEach group as a separate line overlay. Suitable for a small number of groups.

Normalization

OptionDescription
Absolute valuesDisplay raw resource units, hours, or cost.
Per unit capacityNormalise values as a fraction of configured capacity.
Peak = 100%Normalise all values to the peak period = 100%.

Capacity source and overload highlighting

PropertyDescription
Capacity sourceFixed value, a field from the data source, or a separate data section (e.g., a resource calendar section).
Overload thresholdPeriods where demand exceeds the threshold percentage of capacity are highlighted.
Overload highlight colorColor applied to overloaded bars or periods (default: red or amber).
Capacity line styleSolid, dashed, or dotted.

Display options

OptionDescription
Data date lineVertical line at the status/data date.
Period label formatMonth name, year-month, week number, or custom format.
Value axis formatInteger, decimal, currency, or abbreviated (K/M).
Baseline bar positionBehind actual (overlap) or beside actual (side by side).

Good practice

  • Use Periodic loading for weekly resourcing decisions and Cumulative for overall project budget management.
  • Always configure a capacity line when the report is used for capacity management to make overloads visible.
  • For formal project status reports, the Baseline vs. Actual preset provides clear evidence of resource performance against plan.
  • Keep the Group by field to ≤ 6 groups; beyond that, stacked charts become difficult to read.